A-Z Instructionals

From Open Source Ecology
Jump to navigation Jump to search

CEB instructionals to be transfered to Make Projects
CEB instructionals CAD Requests

Fabrication

Note: All make pages need a BOM for steps.

  1. Simple Plates
  2. Frame structural support components-Still needs fab drawings
  3. Shaker Mount-Still needs fab drawings
  4. Shaker Hammer and Shaft-Still needs fab drawings
  5. Hopper Supports and Grate Mounts
  6. Shaker Assembly -Still needs fab drawings, assembling hydraulics needs to be above this.
  7. Hopper Sheet Metal-Still needs fab drawings
  8. Soil Loading Drawer-Still needs fab drawings


Still need to be added in MAKE:

Soil Loading System

Machine Core

Frame Preparation

Assembling the frame

You'll need to have finished all other components in Machine Core and Frame Preparation and 2 Leg Holders

Hydraulics

Assembly

Before beginning assembly, insure you have finished all of the components listed above in the fabrication step.

  1. Assemble the structural components
  2. Assemble the Soil Loading System
  3. Adjust the Drawer
  4. Install the secondary cylinder
  5. Hard-line the main cylinder

Programming

An Arduino is the microprocessor that controls the CEB Press's actions. It must be programmed with the CEB Press's unique program for making bricks.

Source code can be found at github: https://github.com/OSE/ceb-controller

Old code: