This page gives you all the information you need to make your CEB Press from stock steel and parts. First, obtain all of the items listed in the Bill of Materials. Then consult the Cut List and cut all steel to size. From there, fabricate the individual parts and assemblies by following the steps listed under '''Fabrication'''. Finish mechanical assembly by completing the steps in the '''Assembly''' section. Once the machine is completed mechanically, paint the machine. Then make the electronic components and install them. Follow the procedures listed in the testing section to integrate the mechanics, hydraulics, and electronics.
This page gives you all the information you need to make your CEB Press from stock steel and parts. The steps in '''Mechanical Fabrication''' and '''Electronic Components''' are independent of each other, but within each category, the suggested order should be followed. Once you finish both, you can continue on to '''Final Machine Integration'''. At that point, your machine can be used.
=[[CEB/Gen3/BOM|Bill of Materials]]=
=[[CEB/Gen3/BOM|Bill of Materials]]=


=Mechanical Fabrication=
=Mechanical Fabrication=
The purpose of this section is to build and assemble all mechanical components of the CEB. You must first cut the steel, then fabricate individual parts, then assemble them, and then paint the machine.
==Steel Cut List==
==Steel Cut List==
*Cut the steel into the following lengths.  
*Cut the steel into the following lengths.  
Line 13: Line 14:
</html><br/>
</html><br/>
[https://docs.google.com/spreadsheet/pub?hl=en_US&hl=en_US&key=0AtAVl-K5-trVdFQ3MHJBZ2h0dFlqcjBib1NnZ25CZGc&output=html Link] to printable page.
[https://docs.google.com/spreadsheet/pub?hl=en_US&hl=en_US&key=0AtAVl-K5-trVdFQ3MHJBZ2h0dFlqcjBib1NnZ25CZGc&output=html Link] to printable page.
==Parts Fabrication==
The purpose of this section is to assemble the cut steel into individual parts and assemblies.
The purpose of this section is to assemble the cut steel into individual parts and assemblies.
*Please see [https://docs.google.com/spreadsheet/pub?hl=en_US&hl=en_US&key=0AtAVl-K5-trVdFdoblptQ2ZlUlBrQ3RHVHk5b1Rmd0E&output=html this spreadsheet] for what steel each step requires.
*Please see [https://docs.google.com/spreadsheet/pub?hl=en_US&hl=en_US&key=0AtAVl-K5-trVdFdoblptQ2ZlUlBrQ3RHVHk5b1Rmd0E&output=html this spreadsheet] for what steel each step requires.


=Parts Fabrication=
===Structural Components===
===Structural Components===
#[http://makeprojects.com/Project/Simple-Plates/1719/1 Simple Plates]
#[http://makeprojects.com/Project/Simple-Plates/1719/1 Simple Plates]

Revision as of 03:41, 23 December 2011

THIS PAGE IS FOR THE CEB PRESS

CEB instructionals CAD Requests
This page gives you all the information you need to make your CEB Press from stock steel and parts. The steps in Mechanical Fabrication and Electronic Components are independent of each other, but within each category, the suggested order should be followed. Once you finish both, you can continue on to Final Machine Integration. At that point, your machine can be used.

Bill of Materials

Mechanical Fabrication

The purpose of this section is to build and assemble all mechanical components of the CEB. You must first cut the steel, then fabricate individual parts, then assemble them, and then paint the machine.

Steel Cut List

  • Cut the steel into the following lengths.
  • Label and separate cuts by "Step" number so you can easily find cuts for each step during the fabrication stage.
  • Note: Item Number and part number refer to CAD information. This is un-necessary if you are following the fabrication steps listed.


Link to printable page.

Parts Fabrication

The purpose of this section is to assemble the cut steel into individual parts and assemblies.

Structural Components

  1. Simple Plates
  2. Frame structural support components-Still needs fab drawings

Soil Loading System

Shaker

  1. Shaker Mount
  2. Shaker Hammer and Shaft
  3. Shaker Hydraulics

Hopper and Grate

  1. Hopper and Grate Supports
  2. Hopper Sheet Metal-Still needs fab drawings
  3. Hopper Mounting plate
  4. Grate-Still needs fab drawings

Machine Core

  1. Soil Loading Drawer
  2. Roller Guides

Main Frame

Main Frame Preparation
  1. Wide Cylinder Supports
  2. Main Frame Small Components
  3. Main Frame U-Channel Prep-Still needs fab drawings
Main Cylinder Preparation
  1. Make the Press Feet
  2. Prepare the main cylinder
Main Frame Assembly
  1. Assemble U Channel
  2. Fit the Main Cylinder
  3. Stretch the frame
  4. Weld the spacers
  5. Install Small Components
  6. Fit the Drawer Members


Still need to be added in MAKE:

Parts Assembly

The purpose of this section is to assemble all of the parts you made in the fabrication section.

  1. Assemble the structural components
  2. Assemble the Soil Loading System
  3. Shaker Assembly
  4. Adjust the Drawer
  5. Install the secondary cylinder
  6. Hard-line the main cylinder

Paint

  • Cover the hydraulics and any other place that should not be painted.
  • Check all external surfaces for sharp edges and smooth with angle grinder.
  • Remove any surface rust with wire brush and / or sandpaper.
  • Apply a thorough coating of paint to all steel surfaces.
  • Allow 24 hours to dry before handling.

Hydraulics

Note: x represents an unfinished page.

  1. Solenoid Valve x

Electronic Components Assembly

  1. Linked Extension Cord
  2. Sensor Unit
  3. Case
  4. Solenoid Driver x
  5. Controller Box

Final Machine Integration

  1. Mount Solenoid Valve Set And Controller Box x
  2. Electrohydraulic Integration
  3. Code Upload



Programming

An Arduino is the microprocessor that controls the CEB Press's actions. It must be programmed with the CEB Press's unique program for making bricks.

Source code can be found at github: https://github.com/OSE/ceb-controller

Old code: