January Milestone and Strategy Brief: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
Line 9: Line 9:
#January 7 - disseminate [[OSE Enterprise Plan]] far and wide to seed the acquisition of the remaining $5M of $5.5M by April 1, 2012
#January 7 - disseminate [[OSE Enterprise Plan]] far and wide to seed the acquisition of the remaining $5M of $5.5M by April 1, 2012
#January 31 - recuit [[Co-Founder]] or CEO, [[Build Naturally Workshop]] Organizer, and [[OSE Blogger]], [[Farmer]], [[Builder]], and [[Production Manager]]
#January 31 - recuit [[Co-Founder]] or CEO, [[Build Naturally Workshop]] Organizer, and [[OSE Blogger]], [[Farmer]], [[Builder]], and [[Production Manager]]
#'''CEB Press''' - build a CEB Press on a trailer - Jan. 15
#'''CEB Press''' - build a CEB Press on a trailer - Jan. 15. Document trailer fully by Jan 31 via remote CAD documentation.
#'''Sawmill''' - finish build by January 15 - put in 8 hours of testing by January 31. Recruiting [[Sawyer]] for this.
#'''Sawmill''' - finish build by January 15 - put in 8 hours of testing by January 31. Recruiting [[Sawyer]] for testing phase after Jan. 15.

Revision as of 02:56, 1 January 2012

Intro

As a general perspective - 12 projects need to be run in parallel, with a monthly prototyping cycle for 3 prototypes - to deliver the full GVCS by Dec. 21, 2011. There are 355 days left.


CEBhybrid.jpg

GVCS Milestones and Strategy

  1. January 7 - disseminate OSE Enterprise Plan far and wide to seed the acquisition of the remaining $5M of $5.5M by April 1, 2012
  2. January 31 - recuit Co-Founder or CEO, Build Naturally Workshop Organizer, and OSE Blogger, Farmer, Builder, and Production Manager
  3. CEB Press - build a CEB Press on a trailer - Jan. 15. Document trailer fully by Jan 31 via remote CAD documentation.
  4. Sawmill - finish build by January 15 - put in 8 hours of testing by January 31. Recruiting Sawyer for testing phase after Jan. 15.