*Cloverdale steel order ongoing due to machining issues. Cloverdale to provide pick up date as soon as possible.
*Cloverdale steel order ongoing due to machining issues. Cloverdale to provide pick up date as soon as possible.
*Executive Staff Meeting with Catherine scheduled for Tuesday at 5PM CST, scheduled in OSE Schedule
*Executive Staff Meeting with Catherine scheduled for Tuesday at 5PM CST, scheduled in OSE Schedule
*Separated funds spend on CEB and Hablab consumables on three of the enclosed spreadsheet, [https://docs.google.com/a/opensourceecology.org/spreadsheet/ccc?key=0ArpE5Y9PpJCXdFJMX3VWWVB5Y3NraExtaUgzWlhSTmc#gid=7 OSE Budget]


==Wed Sept 04, 2013==
==Wed Sept 04, 2013==

Revision as of 18:38, 5 September 2013

Thurs Sept 04, 2013

  • Cloverdale steel order ongoing due to machining issues. Cloverdale to provide pick up date as soon as possible.
  • Executive Staff Meeting with Catherine scheduled for Tuesday at 5PM CST, scheduled in OSE Schedule
  • Separated funds spend on CEB and Hablab consumables on three of the enclosed spreadsheet, OSE Budget

Wed Sept 04, 2013

Tues Sept 03, 2013

Mon Sept 02, 2013

Sun Sept 01, 2013