January Milestone and Strategy Brief: Difference between revisions
Jump to navigation
Jump to search
Line 9: | Line 9: | ||
#January 7 - disseminate [[OSE Enterprise Plan]] far and wide to seed the acquisition of the remaining $5M of $5.5M by April 1, 2012 | #January 7 - disseminate [[OSE Enterprise Plan]] far and wide to seed the acquisition of the remaining $5M of $5.5M by April 1, 2012 | ||
#January 31 - recuit [[Co-Founder]] or CEO, [[Build Naturally Workshop]] Organizer, and [[OSE Blogger]], [[Farmer]], [[Builder]], and [[Production Manager]] | #January 31 - recuit [[Co-Founder]] or CEO, [[Build Naturally Workshop]] Organizer, and [[OSE Blogger]], [[Farmer]], [[Builder]], and [[Production Manager]] | ||
#'''CEB Press''' - build a CEB Press on a trailer - Jan. 15. Document trailer fully by Jan 31 via remote CAD documentation. | #'''CEB Press''' - build a CEB Press on a trailer - Jan. 15. Document trailer fully by Jan 31 via remote CAD documentation. Status: delays possible with Sweiger production schedule. | ||
#'''Dimensional Sawmill''' - finish build by January 15 by having [[Sweiger Shop]] finish the build - put in 8 hours of testing by January 31. Recruiting [[Sawyer]] for testing phase after Jan. 15. Purchase outstanding hydraulic motors by Jan. 1, 2012. | #'''Dimensional Sawmill''' - finish build by January 15 by having [[Sweiger Shop]] finish the build - put in 8 hours of testing by January 31. Recruiting [[Sawyer]] for testing phase after Jan. 15. Purchase outstanding hydraulic motors by Jan. 1, 2012. Status: delays possible with Sweiger production schedule. | ||
#'''Ironworker Machine''' - Prototype 2 by Janauary 31. with Brianna sourcing blades and following the Scotchman design. See [[Ironworker Prototype II]] page. | #'''Ironworker Machine''' - Prototype 2 by Janauary 31. with Brianna sourcing blades and following the Scotchman design. See [[Ironworker Prototype II]] page. Status: good. | ||
#'''CNC Circuit Mill''' - parts being sourced; prototype completion as scheduled. Status: good. |
Revision as of 03:14, 1 January 2012
Intro
As a general perspective - 12 projects need to be run in parallel, with a monthly prototyping cycle for 3 prototypes - to deliver the full GVCS by Dec. 21, 2011. There are 355 days left.
GVCS Milestones and Strategy
- January 7 - disseminate OSE Enterprise Plan far and wide to seed the acquisition of the remaining $5M of $5.5M by April 1, 2012
- January 31 - recuit Co-Founder or CEO, Build Naturally Workshop Organizer, and OSE Blogger, Farmer, Builder, and Production Manager
- CEB Press - build a CEB Press on a trailer - Jan. 15. Document trailer fully by Jan 31 via remote CAD documentation. Status: delays possible with Sweiger production schedule.
- Dimensional Sawmill - finish build by January 15 by having Sweiger Shop finish the build - put in 8 hours of testing by January 31. Recruiting Sawyer for testing phase after Jan. 15. Purchase outstanding hydraulic motors by Jan. 1, 2012. Status: delays possible with Sweiger production schedule.
- Ironworker Machine - Prototype 2 by Janauary 31. with Brianna sourcing blades and following the Scotchman design. See Ironworker Prototype II page. Status: good.
- CNC Circuit Mill - parts being sourced; prototype completion as scheduled. Status: good.