Katie 2013 Log: Difference between revisions

From Open Source Ecology
Jump to navigation Jump to search
No edit summary
Line 1: Line 1:
==Thurs Sept 04, 2013==
==Thurs Sept 04, 2013==


*Cloverdale steel order ongoing due to machining issues. Cloverdale to provide pick up date as soon as possible.  
*Cloverdale steel order ongoing due to machining issues. Cloverdale to provide pick up date as soon as possible.
*Executive Staff Meeting with Catherine scheduled for Tuesday at 5PM CST, scheduled in OSE Schedule


==Wed Sept 04, 2013==
==Wed Sept 04, 2013==

Revision as of 17:03, 5 September 2013

Thurs Sept 04, 2013

  • Cloverdale steel order ongoing due to machining issues. Cloverdale to provide pick up date as soon as possible.
  • Executive Staff Meeting with Catherine scheduled for Tuesday at 5PM CST, scheduled in OSE Schedule

Wed Sept 04, 2013

Tues Sept 03, 2013

Mon Sept 02, 2013

Sun Sept 01, 2013

Archived Katie Log August 2013

Archived Katie Log July 2013

Archived Katie Log June 2013

Archived Katie Log March-May 2013