OSE has demonstrated significant [[Milestones]] in development time compression - such as:
OSE has demonstrated significant [[Milestones]] in development time compression - such as:


*2021 - we have documented that the build time of the first floor walls of a 500 sf footprint Seed Eco-Home is 1 hour 18 minutes, with effectively 8 people working.
*2021 - we have documented that the build time of the first floor walls of a 500 sf footprint Seed Eco-Home is 1 hour 18 minutes, with 8 people working and rest watching.
*[[MicroTrac v17.10]] built in 5 days in a public workshop with about 12 people
*[[MicroTrac v17.10]] built in 5 days in a public workshop with about 12 people
*FIrst 5 day build of a 1400 sf home achieved, with exterior finished but not interior. [[Seed_Eco-Home#November_2016_Build]]
*FIrst 5 day build of a 1400 sf home achieved, with exterior finished but not interior. [[Seed_Eco-Home#November_2016_Build]]

Revision as of 01:29, 2 June 2025

A number that corresponds to the factor of time decrease - when tasks are done in parallel as opposed to sequentially - in an open source product development process. This requires Swarming and Module Based Design

OSE has demonstrated significant Milestones in development time compression - such as:

  • 2021 - we have documented that the build time of the first floor walls of a 500 sf footprint Seed Eco-Home is 1 hour 18 minutes, with 8 people working and rest watching.
  • MicroTrac v17.10 built in 5 days in a public workshop with about 12 people
  • FIrst 5 day build of a 1400 sf home achieved, with exterior finished but not interior. Seed_Eco-Home#November_2016_Build
  • 2016 - One day build of 3D printer achieved in 2016, using an open source kit - where 12 3D printers were built in one day for people to take home with them.
  • 2013 - Full size tractor built in 5 days with 8 people. See LifeTrac 5.
  • Redesign/build of the ironworker shear in 2 days instead of 6 months of the previous version in 2012. See Ironworker 3.
  • 2012 - Industrial productivity achieved on a small scale, with the first 1 day build of a heavy machine - the CEB Press - was achieved with 12 people.