Revision as of 01:44, 19 June 2011
Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required and allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
- Draw up personnel plan, detailed
Power Cube Tasks
Prepare Electrical System Components
Tractor Tasks
Wheel Shafts
- Cut 1-7/8" shafts to 28"
- Cut 6" long collars from 2" pipe
- Label collar and shaft, as these are paired up and can't be confused between shafts.
- Drill 3/4" hole for wheel plate mounting through shaft and collar
- Drill through collar and shaft at the same time
- Weld on reinforcing nuts on collars
- End drill 3.5" deep (on a lathe) the 1-3/8" receiver for 6-spline standard PTO shafting
Wheel Mounting Plates
- Prepare plates, 4 per tractor - 8x10x1/2"
- Download CAM files for wheel plates -[1]
- Configure LinuxCNC
- Torch out plates (or cut by hand)
- Cut gussets - right angle triangles with 4" legs - 4 per wheel
- Weld gussets onto plates
Hydraulic Motor Interface Plates
- Prepare plates, 4 per tractor - 6x8x1/2"
- Download CAM files for interface plates - []
- Torch out plates (or cut by hand)
Hydraulic Motor Mount Plates
- Prepare plates, 4 per tractor, 8x10x1/2"
- Download CAM files -[]
- Torch out plates (or cut by hand)
Secondary Cylinder Mount, bottom
May Production Run New Generator Tasks
May Production Run Generator Tasks