Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required and allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
- Draw up personnel plan, detailed
Power Cube Tasks
Prepare Electrical System Components
Tractor Tasks
Wheel Mounting Plates
- Prepare plates, 4 per tractor - 8x10x1/2"
- Download CAM files for wheel plates -[1]
- Configure LinuxCNC
- Torch out plates (or cut by hand)
- Cut gussets - right angle triangles with 4" legs - 4 per wheel
- Weld gussets onto plates
Hydraulic Motor Interface Plates
- Prepare plates, 4 per tractor - 6x8x1/2"
- Download CAM files for interface plates - []
- Torch out plates (or cut by hand)
Hydraulic Motor Mount Plates
- Prepare plates, 4 per tractor, 8x10x1/2"
- Download CAM files -[]
- Torch out plates (or cut by hand)
May Production Run New Generator Tasks