May Production Plan: Difference between revisions
Jump to navigation
Jump to search
(4 intermediate revisions by the same user not shown) | |||
Line 41: | Line 41: | ||
'''[[Mount Motors]]''' | '''[[Mount Motors]]''' | ||
'''[[Mount Wheels]]''' | '''[[Mount Wheels]]''' - fabricate wheel mounting plates | ||
'''[[Assemble H-arms]]''' | '''[[Assemble H-arms]]''' | ||
'''[[Mount | '''[[Mount QA Plates]]''' | ||
'''[[ | '''[[Mount Cylinders]]''' | ||
Then final assembly: | |||
'''[[Insert Wheel Shaft Assemblies into Bearings]]''' | |||
'''[[Mount | '''[[Build Wheel Motor Assemblies and Mount on Tractor]]''' | ||
=Hydraulic Motor Interface Plates= | =Hydraulic Motor Interface Plates= |
Latest revision as of 21:23, 23 June 2011
Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required and allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
- Draw up personnel plan, detailed
Power Cube Tasks
Prepare Electrical System Components
Tractor Tasks
Mount Wheels - fabricate wheel mounting plates
Then final assembly:
Insert Wheel Shaft Assemblies into Bearings
Build Wheel Motor Assemblies and Mount on Tractor
Hydraulic Motor Interface Plates
- Prepare plates, 4 per tractor - 6x8x1/2"
- Download CAM files for interface plates - []
- Torch out plates (or cut by hand)
Hydraulic Motor Mount Plates
- Prepare plates, 4 per tractor, 8x10x1/2"
- Download CAM files -[]
- Torch out plates (or cut by hand)
May Production Run New Generator Tasks
May Production Run Generator Tasks