*List steps in order of duty – Power Cube to Tractor to CEB press | *List steps in order of duty – Power Cube to Tractor to CEB press | ||
*Assess capacity required | *Assess capacity required and allocate tasks to 6 fabricators and local shop | ||
*List risks and recovery plans | *List risks and recovery plans | ||
*Assess daily, before and after workday | *Assess daily, before and after workday | ||
*Draw up personnel plan, detailed | *Draw up personnel plan, detailed | ||
=Power Cube Tasks= | =Power Cube Tasks= | ||
See [[Power Cube Documentation]] | |||
'''[[Build Hydraulic Tank]]''' | |||
''' | '''[[Build Fuel Tank]]''' | ||
''' | '''[[Prepare Electrical System Components]]''' | ||
'''[[Build Mufflers]]''' | |||
''' | '''[[Assemble Power Cube]] | ||
'''[[Mount Power Cube]]''' | |||
''' | '''[[Test Power Cube on Tractor]]''' | ||
=Tractor Tasks= | |||
See [[Tractor Documentation]] | |||
'''[[Build Frame]]''' | |||
''' | '''[[Build QA Plate]]''' | ||
'''[[Build Wheel Shaft Attachments]]''' | |||
'''[[Build Wheel Shafts]]''' | |||
''' | '''[[Mount Motors]]''' | ||
'''Mount | '''[[Mount Wheels]]''' - fabricate wheel mounting plates | ||
''' | '''[[Assemble H-arms]]''' | ||
'''Mount | '''[[Mount QA Plates]]''' | ||
'''[[Mount Cylinders]]''' | |||
Then final assembly: | |||
''' | '''[[Insert Wheel Shaft Assemblies into Bearings]]''' | ||
'''Wheel | '''[[Build Wheel Motor Assemblies and Mount on Tractor]]''' | ||
=Hydraulic Motor Interface Plates= | |||
*Prepare plates, 4 per tractor - 6x8x1/2" | *Prepare plates, 4 per tractor - 6x8x1/2" | ||
*Download CAM files for interface plates - [] | *Download CAM files for interface plates - [] | ||
Line 204: | Line 61: | ||
=Hydraulic Motor Mount Plates= | |||
*Prepare plates, 4 per tractor, 8x10x1/2" | *Prepare plates, 4 per tractor, 8x10x1/2" | ||
*Download CAM files -[] | *Download CAM files -[] | ||
*Torch out plates (or cut by hand) | *Torch out plates (or cut by hand) | ||
=May Production Run New Generator Tasks= | =May Production Run New Generator Tasks= |
Latest revision as of 21:23, 23 June 2011
Strategy:
- List steps in order of duty – Power Cube to Tractor to CEB press
- Assess capacity required and allocate tasks to 6 fabricators and local shop
- List risks and recovery plans
- Assess daily, before and after workday
- Draw up personnel plan, detailed
Power Cube Tasks
Prepare Electrical System Components
Tractor Tasks
Mount Wheels - fabricate wheel mounting plates
Then final assembly:
Insert Wheel Shaft Assemblies into Bearings
Build Wheel Motor Assemblies and Mount on Tractor
Hydraulic Motor Interface Plates
- Prepare plates, 4 per tractor - 6x8x1/2"
- Download CAM files for interface plates - []
- Torch out plates (or cut by hand)
Hydraulic Motor Mount Plates
- Prepare plates, 4 per tractor, 8x10x1/2"
- Download CAM files -[]
- Torch out plates (or cut by hand)
May Production Run New Generator Tasks