CEB Press/Manufacturing Instructions/Hopper sheet metal
Jump to navigation
Jump to search
|
Warning: The documentation for the CEB Press is undergoing a thorough overhaul. CAD models and written directions are presently obsolete. For more information, see Talk:CEB_Press#Documentation_overhaul_in_progress. When the models, specifications and text on this article have been thoroughly reviewed, updated when necessary, and confirmed as whole and accurate, this warning may be removed.
Tools Required
- torch
- welder
- hole punch
Materials Required
- hinges
- 3/4" bolts
- 1/2" bolts
- one 5X10 or two 4X8 sheets of metal.
Diagrams
Fabrication Steps
- Plasma cut sheet metal
- Punch 3/4" holes in all 28 hinges, in center of rounded part
- Punch holes in hopper sheet metal (all the blue holes, 3/4")
- Bolt all hinges to sheet metal at the red locations marked "1" with 3/4" bolts
- Weld bottom hinges of hopper sheet 1 to hopper mount plate
- Weld top hinges of hopper sheet 1 to grate
- Install hopper supports to hold hopper sheet 1, and bolt with the 2 bolts (1/2")
- Weld hinges to hopper supports for sheet 2
- Weld hinges at base of sheets 2, 3, 4
- Weld hinges between sheets 3&1, 4&1, and between 2&3, and 2&4
- At this point, the entire hopper is erected. It remains to weld the remaining hinges to the grate.
- Upon completing these steps, the 3/4" bolts can be replaced with 1/2" bolts for successive deconstruction and reconstruction of the hopper.