'''The entire fabrication procedure is contained in a master PDF file - [[Media:CEB_a-z_Build_1.0.pdf|CEB A-Z Fabrication Instructions 2011]]''' | '''The entire fabrication procedure is contained in a master PDF file - [[Media:CEB_a-z_Build_1.0.pdf|CEB A-Z Fabrication Instructions 2011]]''' | ||
=Tools and Materials= | =Prototype IV Fabrication= | ||
==Drawer== | |||
See Fabrication Diagram and Master Index for part numbers | |||
#Tack two sets of 70 and 71 together | |||
##Instead of 5/8" thickness for 70, use 1/2" thickness on one rail | |||
##Tack so that 5/8" can be replaced with 1/2" if needed | |||
##Grind tacks off top | |||
##QC - work on a flat surface, so top side is within 1/64" inch even for both rails | |||
##QC - tacks ground down to surface of rails as can be felt with a flat surface | |||
=Tools and Materials for Prototype III= | |||
*'''Spreadsheet''' | *'''Spreadsheet''' | ||
Line 20: | Line 31: | ||
https://docs.google.com/spreadsheet/ccc?key=0AlpsBarfpPkzdHF1TmxZQnVTU1dxbGF1a0V3MmZfcUE | https://docs.google.com/spreadsheet/ccc?key=0AlpsBarfpPkzdHF1TmxZQnVTU1dxbGF1a0V3MmZfcUE | ||
=Mechanical Fabrication= | =Mechanical Fabrication= | ||
Line 38: | Line 48: | ||
===Structural Components=== | ===Structural Components=== | ||
#[http://makeprojects.com/Project/Simple-Plates/1719/1 Simple Plates] | #[http://makeprojects.com/Project/Simple-Plates/1719/1 Simple Plates] <-link broken ? | ||
#[http://makeprojects.com/Project/CEB-Support-System/1718/1 Frame structural support components] | #[http://makeprojects.com/Project/CEB-Support-System/1718/1 Frame structural support components] | ||
Line 49: | Line 59: | ||
<ol><li value="6">[http://makeprojects.com/Project/CEB-Hopper-Supports-and-Grate-Supports/1722/1 Hopper and Grate Supports] | <ol><li value="6">[http://makeprojects.com/Project/CEB-Hopper-Supports-and-Grate-Supports/1722/1 Hopper and Grate Supports] | ||
<li>[http://makeprojects.com/Project/Prepare-the-Hopper-Sheet-Metal/1723/1 Hopper Sheet Metal] | <li>[http://makeprojects.com/Project/Prepare-the-Hopper-Sheet-Metal/1723/1 Hopper Sheet Metal] | ||
<li>[http://makeprojects.com/Project/Hopper-Mounting-Plate/1732/1 Hopper Mounting plate] | <li>[http://makeprojects.com/Project/Hopper-Mounting-Plate/1732/1 Hopper Mounting plate] <-link broken ? | ||
<li>[http://makeprojects.com/Project/CEB-Soil-Grate/1731/1 Grate]</ol> | <li>[http://makeprojects.com/Project/CEB-Soil-Grate/1731/1 Grate]</ol> | ||
===Machine Core=== | ===Machine Core=== | ||
<ol><li value="10">[http://makeprojects.com/Project/Soil-Loading-Drawer/1724/1 Soil Loading Drawer] | <ol><li value="10">[http://makeprojects.com/Project/Soil-Loading-Drawer/1724/1 Soil Loading Drawer] | ||
<li>[http://makeprojects.com/Project/Roller-Guides/1730/1 Roller Guides]</ol> | <li>[http://makeprojects.com/Project/Roller-Guides/1730/1 Roller Guides]</ol><-link 11 broken ? | ||
===Main Frame Preparation=== | ===Main Frame Preparation=== | ||
Line 60: | Line 70: | ||
<li>[http://makeprojects.com/Project/CEB-Main-Frame-Small-components/1736/1 Main Frame Small Components] | <li>[http://makeprojects.com/Project/CEB-Main-Frame-Small-components/1736/1 Main Frame Small Components] | ||
<li>[http://makeprojects.com/Project/CEB-Main-Frame-U-Channel-Prep/1737/1 Main Frame U-Channel Prep]-Still needs fab drawings</ol> | <li>[http://makeprojects.com/Project/CEB-Main-Frame-U-Channel-Prep/1737/1 Main Frame U-Channel Prep]-Still needs fab drawings</ol> | ||
<ol><li value="15">[http://makeprojects.com/Project/CEB-Press-Feet/1738/1 Make the Press Feet] | <ol><li value="15">[http://makeprojects.com/Project/CEB-Press-Feet/1738/1 Make the Press Feet] <-link broken? | ||
<li>[http://makeprojects.com/Project/CEB-Main-Cylinder-Prep/1739/1 Prepare the main cylinder]</ol> | <li>[http://makeprojects.com/Project/CEB-Main-Cylinder-Prep/1739/1 Prepare the main cylinder]</ol> | ||
Line 94: | Line 104: | ||
#[[CEB Press/Manufacturing Instructions/Sensor Unit|Sensor Unit]] | #[[CEB Press/Manufacturing Instructions/Sensor Unit|Sensor Unit]] | ||
#[[CEB Press/Manufacturing Instructions/Case|Case]] | #[[CEB Press/Manufacturing Instructions/Case|Case]] | ||
#[ | #[[CEB_Press/Manufacturing_Instructions/Detroit_Fab_Lab_Solenoid_Driver_v2|Solenoid Driver v2]] | ||
#[[CEB Press/Manufacturing Instructions/Controller Box|Controller Box]] | #[[CEB Press/Manufacturing Instructions/Controller Box|Controller Box]] | ||
=Final Machine Integration= | =Final Machine Integration= | ||
#[[CEB Press/Manufacturing Instructions/Mount Solenoid Valve Set And Controller Box|Mount Solenoid Valve Set | #[[CEB Press/Manufacturing Instructions/Mount Solenoid Valve Set And Controller Box|Mount Solenoid Valve Set, Controller Box and Sensors]] | ||
#[[CEB Press/Manufacturing Instructions/ElectrohydraulicIntegration|Electrohydraulic Integration]] | #[[CEB Press/Manufacturing Instructions/ElectrohydraulicIntegration|Electrohydraulic Integration]] | ||
#[[CEB Press | #[[CEB_Press_Control_Code|CEB Press Control Code]] | ||
{{GVCS Footer}} | {{GVCS Footer}} | ||
{{Civilization_Starter_Kit_DVD}} | {{Civilization_Starter_Kit_DVD}} |
Latest revision as of 00:15, 20 July 2014
CEB Press | ||
---|---|---|
Home | Research & Development | Bill of Materials | Manufacturing Instructions | User's Manual | User Reviews | ![]() |
Overview
This page gives you all the information you need to make your CEB Press from stock steel and parts. The steps in Mechanical Fabrication and Electronic Components are independent of each other, but within each category, the suggested order should be followed. Once you finish both, you can continue on to Final Machine Integration. At that point, your machine can be used.
The entire fabrication procedure is contained in a master PDF file - CEB A-Z Fabrication Instructions 2011
Prototype IV Fabrication
Drawer
See Fabrication Diagram and Master Index for part numbers
- Tack two sets of 70 and 71 together
- Instead of 5/8" thickness for 70, use 1/2" thickness on one rail
- Tack so that 5/8" can be replaced with 1/2" if needed
- Grind tacks off top
- QC - work on a flat surface, so top side is within 1/64" inch even for both rails
- QC - tacks ground down to surface of rails as can be felt with a flat surface
Tools and Materials for Prototype III
- Spreadsheet
- Edit
https://docs.google.com/spreadsheet/ccc?key=0AlpsBarfpPkzdHF1TmxZQnVTU1dxbGF1a0V3MmZfcUE
Mechanical Fabrication
The purpose of this section is to build and assemble all mechanical components of the CEB. You must first cut the steel, then fabricate individual parts, then assemble them, and then paint the machine.
Steel Cut List
- Cut the steel into the following lengths.
- Label and separate cuts by "Step" number so you can easily find cuts for each step during the fabrication stage.
- Note: Item Number and part number refer to CAD information. This is un-necessary if you are following the fabrication steps listed.
- Also, from the sheet, torch the Hopper Sheet Metal and the simple plates.
Link to printable page.
Parts Fabrication
The purpose of this section is to assemble the cut steel into individual parts and assemblies.
- Please see this spreadsheet for what steel each step requires.
Structural Components
- Simple Plates <-link broken ?
- Frame structural support components
Shaker
Hopper and Grate
- Hopper and Grate Supports
- Hopper Sheet Metal
- Hopper Mounting plate <-link broken ?
- Grate
Machine Core
<-link 11 broken ?
Main Frame Preparation
- Wide Cylinder Supports
- Main Frame Small Components
- Main Frame U-Channel Prep-Still needs fab drawings
- Make the Press Feet <-link broken?
- Prepare the main cylinder
Main Frame Assembly
- Assemble U Channel
- Fit the Main Cylinder
- Stretch the frame
- Weld the spacers
- Install Small Components
- Fit the Drawer Members
Hydraulics
Parts Assembly
The purpose of this section is to assemble all of the parts you made in the parts fabrication section.
- Assemble the structural components
- Assemble the Soil Loading System
- Shaker Assembly
- Adjust the Drawer
- Install the secondary cylinder
- Hard-line the main cylinder
Paint
- Cover the hydraulics and any other place that should not be painted.
- Check all external surfaces for sharp edges and smooth with angle grinder.
- Remove any surface rust with wire brush and / or sandpaper.
- Apply a thorough coating of paint to all steel surfaces.
- Allow 24 hours to dry before handling.
Electronic Components Assembly
Final Machine Integration
- Mount Solenoid Valve Set, Controller Box and Sensors
- Electrohydraulic Integration
- CEB Press Control Code